以乌锡铁路黄河特大桥穿越滩涂地区不良地质为例,对箱梁预制拼装和支架现浇两种方案在经济、安全、工期等方面进行对比,并侧重介绍了支架现浇施工方案.
以烏錫鐵路黃河特大橋穿越灘塗地區不良地質為例,對箱樑預製拼裝和支架現澆兩種方案在經濟、安全、工期等方麵進行對比,併側重介紹瞭支架現澆施工方案.
이오석철로황하특대교천월탄도지구불량지질위례,대상량예제병장화지가현요량충방안재경제、안전、공기등방면진행대비,병측중개소료지가현요시공방안.
Taking the unfavorable geological conditions of area of Wuxi railway Yellow River bridge crossing the beach, the paper compares the two programs, box girder precast and assembly and support cast, in economy, security and construction period, and focuses on support cast construction program.