泰安煤矿针对8103综采工作面的顶板危害,为保老顶初次来压期间的安全生产,期望破坏顶板的完整性、能使顶板及时垮落,改善周期来压步距,缓解老顶周期来压的巨大载荷,要在工作面实施深孔预裂爆破强制放顶技术,并且辅助安全措施,实际效果明显。
泰安煤礦針對8103綜採工作麵的頂闆危害,為保老頂初次來壓期間的安全生產,期望破壞頂闆的完整性、能使頂闆及時垮落,改善週期來壓步距,緩解老頂週期來壓的巨大載荷,要在工作麵實施深孔預裂爆破彊製放頂技術,併且輔助安全措施,實際效果明顯。
태안매광침대8103종채공작면적정판위해,위보로정초차래압기간적안전생산,기망파배정판적완정성、능사정판급시과락,개선주기래압보거,완해로정주기래압적거대재하,요재공작면실시심공예렬폭파강제방정기술,병차보조안전조시,실제효과명현。
For roof hazard of No.8103 fully-mechanized mining face in Tai'an Mine, forced caving technology with deep hole pre-splitting blasting was used on the working face to ensure the safety production of first weighting of the main roof and the integrity and promptness of the roof when falling, to improve the intervals of periodic weighting, and to relieve the huge load of periodic weighting of the main roof. Combined with auxiliary safety measures, the technology has achieved ideal effects.