六甲水电站1#、2#机组原主轴密封均采用橡胶平板式密封方式,设备运行期间顶盖漏水量大,时常因抽水泵故障导致水淹水导轴承,针对这一问题对水轮机主轴密封型式和排水方式进行改造。改造后,节省排水能耗和检修费用,运行3年效果良好。
六甲水電站1#、2#機組原主軸密封均採用橡膠平闆式密封方式,設備運行期間頂蓋漏水量大,時常因抽水泵故障導緻水淹水導軸承,針對這一問題對水輪機主軸密封型式和排水方式進行改造。改造後,節省排水能耗和檢脩費用,運行3年效果良好。
륙갑수전참1#、2#궤조원주축밀봉균채용상효평판식밀봉방식,설비운행기간정개루수량대,시상인추수빙고장도치수엄수도축승,침대저일문제대수륜궤주축밀봉형식화배수방식진행개조。개조후,절성배수능모화검수비용,운행3년효과량호。
The main shaft sealing of No.1 and No.2 units of Liujia Hydropower Station was originally flat plate type rubber sealing. Too much leakage from turbine head cover had frequently lead to the turbine guide bearing was flooded due to pump failure. In view of this problem,main shaft sealing and drainage system were modified. Opera?tion of three years since the modification has demonstrate good effects with less pumping energy consumption and maintenance cost.