对一座建于20世纪80年代的跨江拉索斜材体系输电塔的加固方案进行了论述,通过有限元分析确定了该塔的关键受力点及施工荷载限值,进而确定了施工及运行中采用的加固措施,工程仅用2个月完成。
對一座建于20世紀80年代的跨江拉索斜材體繫輸電塔的加固方案進行瞭論述,通過有限元分析確定瞭該塔的關鍵受力點及施工荷載限值,進而確定瞭施工及運行中採用的加固措施,工程僅用2箇月完成。
대일좌건우20세기80년대적과강랍색사재체계수전탑적가고방안진행료논술,통과유한원분석학정료해탑적관건수력점급시공하재한치,진이학정료시공급운행중채용적가고조시,공정부용2개월완성。
This paper discusses reinforcement scheme for one cross-river inhaul cable oblique transmission tower built in the 1980s. By means of finite element analysis,the key force bearing point and construction load limiting value of this tower was determined. Furthermore,reinforcement measures for construction and operation were determined. The engineering was finished only in two months.