某四跨25 m预应力空心板简支梁桥桥墩桩基严重偏位,桩顶最大偏移量为19.1 cm。经分析,该桥桥墩桩基偏位的原因为在堆土不平均土压力作用下,淤泥层发生显著的侧向挤出现象,从而产生巨大的侧向推挤作用,使右幅桥墩产生偏移。结合现场实际情况,采取设置应力释放孔、高压旋喷桩,新增桩基承台及顶推纠偏等措施进行纠偏整治,使桥墩偏位回归允许范围内。采用荷载试验对加固后桥墩的承载能力进行评定,结果表明,桥墩承载能力满足设计要求,所采取的方案有效,纠偏效果良好。
某四跨25 m預應力空心闆簡支樑橋橋墩樁基嚴重偏位,樁頂最大偏移量為19.1 cm。經分析,該橋橋墩樁基偏位的原因為在堆土不平均土壓力作用下,淤泥層髮生顯著的側嚮擠齣現象,從而產生巨大的側嚮推擠作用,使右幅橋墩產生偏移。結閤現場實際情況,採取設置應力釋放孔、高壓鏇噴樁,新增樁基承檯及頂推糾偏等措施進行糾偏整治,使橋墩偏位迴歸允許範圍內。採用荷載試驗對加固後橋墩的承載能力進行評定,結果錶明,橋墩承載能力滿足設計要求,所採取的方案有效,糾偏效果良好。
모사과25 m예응력공심판간지량교교돈장기엄중편위,장정최대편이량위19.1 cm。경분석,해교교돈장기편위적원인위재퇴토불평균토압력작용하,어니층발생현저적측향제출현상,종이산생거대적측향추제작용,사우폭교돈산생편이。결합현장실제정황,채취설치응력석방공、고압선분장,신증장기승태급정추규편등조시진행규편정치,사교돈편위회귀윤허범위내。채용하재시험대가고후교돈적승재능력진행평정,결과표명,교돈승재능력만족설계요구,소채취적방안유효,규편효과량호。
The pile foundations for the piers of a 4 × 25‐m span prestressed concrete simply‐supported hollow slab beam bridge deviated severely and the maximum deviation amount of the pile tops was up to 19 .1 cm .Through the analysis of the deviations of the pile foundations ,it was considered that the causes of the deviations lay in the following :under the action of the non‐uniform stacked soil pressure ,the problem of significant lateral compaction of the silt layers in the ground occurred ,the problem produced enormous lateral pushing action and consequently caused the piers of the right part of the bridge to deviate .In the light of the actual site condi‐tions ,the measures of arranging the stress releasing holes and high pressure jet grouting piles , adding the new pile caps and rectifying the deviations by pushing were taken to handle the devia‐tions of the pile foundations and to restore the deviations of the piers to the allowable range .The bearing capacity of the handled piers was assessed by the load tests and the results showed that that the bearing capacity of the piers could meet the design requirements ,the deviation rectifying scheme prepared for the pile foundations and piers was effective and the effect of the deviation rectifying was sound .