鞍钢技术
鞍鋼技術
안강기술
AISC TECHNIQUES
2015年
1期
31-35
,共5页
赵长城%张磊%金国一%曾宇%赵迪平
趙長城%張磊%金國一%曾宇%趙迪平
조장성%장뢰%금국일%증우%조적평
高炉%降料面%控料线%休风
高爐%降料麵%控料線%休風
고로%강료면%공료선%휴풍
BF%dropping charge level%controlling stockline%shutdown
为了实现鞍钢新2号高炉安全、快速停炉,通过采取炉顶打水、控料线、回收煤气等停炉方案,使降料面过程中各项操作参数得到了合理控制,维持了炉况的稳定顺行,顺利将料面降至炉缸风口区域以下。
為瞭實現鞍鋼新2號高爐安全、快速停爐,通過採取爐頂打水、控料線、迴收煤氣等停爐方案,使降料麵過程中各項操作參數得到瞭閤理控製,維持瞭爐況的穩定順行,順利將料麵降至爐缸風口區域以下。
위료실현안강신2호고로안전、쾌속정로,통과채취로정타수、공료선、회수매기등정로방안,사강료면과정중각항조작삼수득도료합리공제,유지료로황적은정순행,순리장료면강지로항풍구구역이하。
In order to get safe and fast shutdown of the new No.2 blast furnace in General Ironmaking Plant of Angang Steel Co., Ltd., various technical parameters during the dropping charge level are suitably controlled by taking such measures as spraying water from the top of the furnace, controlling the stockline and recovering the gas and therefore the smooth operation of BF is kept and the charge level is lowered below the tuyere zone successfully.