在地下水位高的地区,地下变电站对裂缝控制的要求十分严格。由于存在与地面结构不同的边界约束条件、环境温度与施工过程,对其温度裂缝的研究十分必要。针对上海220 kV 济南变电站工程项目,通过 MIDAS 软件对该剪力墙结构的每一施工工况进行数值模拟,研究温度裂缝的空间分布与随时间的发展变化。结果表明,裂缝主要发生在结构剪力墙纵横墙与楼板等约束较强的交汇处,在浇筑一周后形成,两周内趋于稳定,后续工况中新浇筑的楼层对前工况中楼层的裂缝影响较小,仅存在轻微闭合或扩张。基础底板在浇筑完的第25天内部产生裂缝,在第37天部分内部裂缝连通,基础表面的裂缝形成于基础与墙体的接触处。针对不同的位置与发展程度的温度裂缝,提出相应的措施。
在地下水位高的地區,地下變電站對裂縫控製的要求十分嚴格。由于存在與地麵結構不同的邊界約束條件、環境溫度與施工過程,對其溫度裂縫的研究十分必要。針對上海220 kV 濟南變電站工程項目,通過 MIDAS 軟件對該剪力牆結構的每一施工工況進行數值模擬,研究溫度裂縫的空間分佈與隨時間的髮展變化。結果錶明,裂縫主要髮生在結構剪力牆縱橫牆與樓闆等約束較彊的交彙處,在澆築一週後形成,兩週內趨于穩定,後續工況中新澆築的樓層對前工況中樓層的裂縫影響較小,僅存在輕微閉閤或擴張。基礎底闆在澆築完的第25天內部產生裂縫,在第37天部分內部裂縫連通,基礎錶麵的裂縫形成于基礎與牆體的接觸處。針對不同的位置與髮展程度的溫度裂縫,提齣相應的措施。
재지하수위고적지구,지하변전참대렬봉공제적요구십분엄격。유우존재여지면결구불동적변계약속조건、배경온도여시공과정,대기온도렬봉적연구십분필요。침대상해220 kV 제남변전참공정항목,통과 MIDAS 연건대해전력장결구적매일시공공황진행수치모의,연구온도렬봉적공간분포여수시간적발전변화。결과표명,렬봉주요발생재결구전력장종횡장여루판등약속교강적교회처,재요축일주후형성,량주내추우은정,후속공황중신요축적루층대전공황중루층적렬봉영향교소,부존재경미폐합혹확장。기출저판재요축완적제25천내부산생렬봉,재제37천부분내부렬봉련통,기출표면적렬봉형성우기출여장체적접촉처。침대불동적위치여발전정도적온도렬봉,제출상응적조시。
Temperature crack control of underground substation structures is very strict in areas with high water table.Due to different boundary conditions and constraints,surrounding temperature and construction processes from ground structures,research on temperature cracks of underground substation is necessary.In this paper, MIDAS software was used to simulate the shear wall structure in Shanghai Jinan Road 220 kV substation project. The spatial distribution of temperature cracks and changes with elapsed time was studied through each of the construction conditions.The results show that cracking occurs mainly in the junction of vertical and horizontal shear walls and the junction of walls and floors where strong constraints exist.These cracks are formed in the first week after pouring and become stable in the second week.The subsequent constructed floors have less in-fluence on cracks in the lower floors though only slight fracture closure or expansion occurs.Results also show that cracks inside the foundation formed in the 25th day after pouring and part of them become connected in the 37th day while cracks on the surface of foundation formed at the contact with walls.In this paper,different measures were proposed to control temperature cracks according to different locations and degree.