何新华%胡文发%郭淑婷%陈继红
何新華%鬍文髮%郭淑婷%陳繼紅
하신화%호문발%곽숙정%진계홍
预拌混凝土%泵送%排队理论%仿真%优化
預拌混凝土%泵送%排隊理論%倣真%優化
예반혼응토%빙송%배대이론%방진%우화
ready-miχconcrete%pumping conveyance%queuing method%simulation%optimazation
基于排队理论研究预拌混凝土泵送施工系统的综合性能与配置优化。运用仿真工具建立混凝土泵送施工系统排队仿真模型,探讨混凝土泵车数量变化对系统综合性能的影响规律,发现随着泵车数量的增大,系统性能逐渐变好,泵车繁忙率降低,排队队长和排队时间降低,可服务的混凝土运输车数量增多,且存在一个最优泵车数量值。通过构建混凝土泵送系统最优配置模型,探讨泵车数量、泵车效率、混凝土运输车间隔时间之间的关系,指出提高混凝土泵送施工系统性能的措施。该排队系统仿真模型与实验结果对施工管理具有一定的理论和实践意义。
基于排隊理論研究預拌混凝土泵送施工繫統的綜閤性能與配置優化。運用倣真工具建立混凝土泵送施工繫統排隊倣真模型,探討混凝土泵車數量變化對繫統綜閤性能的影響規律,髮現隨著泵車數量的增大,繫統性能逐漸變好,泵車繁忙率降低,排隊隊長和排隊時間降低,可服務的混凝土運輸車數量增多,且存在一箇最優泵車數量值。通過構建混凝土泵送繫統最優配置模型,探討泵車數量、泵車效率、混凝土運輸車間隔時間之間的關繫,指齣提高混凝土泵送施工繫統性能的措施。該排隊繫統倣真模型與實驗結果對施工管理具有一定的理論和實踐意義。
기우배대이론연구예반혼응토빙송시공계통적종합성능여배치우화。운용방진공구건립혼응토빙송시공계통배대방진모형,탐토혼응토빙차수량변화대계통종합성능적영향규률,발현수착빙차수량적증대,계통성능축점변호,빙차번망솔강저,배대대장화배대시간강저,가복무적혼응토운수차수량증다,차존재일개최우빙차수량치。통과구건혼응토빙송계통최우배치모형,탐토빙차수량、빙차효솔、혼응토운수차간격시간지간적관계,지출제고혼응토빙송시공계통성능적조시。해배대계통방진모형여실험결과대시공관리구유일정적이론화실천의의。
The comprehensive performance and deployment optimization of the ready-mix concrete pumping conveyance and construction system based on queuing method were focused on.The main parameters of the concrete pumping conveyance system were set on the basis of construction engineering practices.An M/M/m queuing model for the concrete pumping conveyance system was established and its performance indicators were analyzed.By applying simulation tools to establish a queuing simulation model for the concrete pumping conveyance system,influences of the number of concrete pumps on the system performance were discussed.It is revealed that while adding more concrete pumps,the system performance is improved,the pumping working time declines,the truck queuing length and time decrease,and more concrete trucks are serviceable.It is obersrved that an optimal number of pumps exsits for the system.An optimal model for deploying the concrete pumping conveyance system was presented,and the relationships among the number of concrete pumps,the efficiency of concrete pumps,and the arrival frequency of concrete trucks were investigated.Several means were suggested to improve the performance of concrete pumping construction system.