探矿工程-岩土钻掘工程
探礦工程-巖土鑽掘工程
탐광공정-암토찬굴공정
EXPLORATION ENGINEERING (DRILLING & TUNNELING)
2015年
2期
22-26
,共5页
任晓顺%太武%刘建福%王建兴%高婷婷%李培林%刘莎莎%孙秀梅
任曉順%太武%劉建福%王建興%高婷婷%李培林%劉莎莎%孫秀梅
임효순%태무%류건복%왕건흥%고정정%리배림%류사사%손수매
深覆盖层%粉砂%卵砾石%泥岩%钻头%冲洗液
深覆蓋層%粉砂%卵礫石%泥巖%鑽頭%遲洗液
심복개층%분사%란력석%니암%찬두%충세액
deep overburden layer%silt%cobble and gravel%mudstone%bit%flushing fluid
河北省乐亭县鲁家坨铁矿区第四系、第三系覆盖层厚,基岩地层破碎,钻探施工过程中坍塌卡钻、缩径、漏涌结合等事故多。选用新型土层专用取心钻具配合常规钻头及特殊金刚石钻头钻进覆盖层,采用加大孔径、优质化学浆液护壁及护孔堵漏相结合措施用绳索取心工艺钻进基岩层,同时强化了泥浆性能调节和维护,加强钻压、转速、大泵量的监护调节等管理措施,顺利完成了施工任务。原设计孔深1300 m,实际终孔深度1408 m,钻孔弯曲度2.9°,岩心采取率覆盖层平均高达80%,岩层100%,矿层100%,成孔周期75天,圆满完成了设计任务书要求,评为优质孔。
河北省樂亭縣魯傢坨鐵礦區第四繫、第三繫覆蓋層厚,基巖地層破碎,鑽探施工過程中坍塌卡鑽、縮徑、漏湧結閤等事故多。選用新型土層專用取心鑽具配閤常規鑽頭及特殊金剛石鑽頭鑽進覆蓋層,採用加大孔徑、優質化學漿液護壁及護孔堵漏相結閤措施用繩索取心工藝鑽進基巖層,同時彊化瞭泥漿性能調節和維護,加彊鑽壓、轉速、大泵量的鑑護調節等管理措施,順利完成瞭施工任務。原設計孔深1300 m,實際終孔深度1408 m,鑽孔彎麯度2.9°,巖心採取率覆蓋層平均高達80%,巖層100%,礦層100%,成孔週期75天,圓滿完成瞭設計任務書要求,評為優質孔。
하북성악정현로가타철광구제사계、제삼계복개층후,기암지층파쇄,찬탐시공과정중담탑잡찬、축경、루용결합등사고다。선용신형토층전용취심찬구배합상규찬두급특수금강석찬두찬진복개층,채용가대공경、우질화학장액호벽급호공도루상결합조시용승색취심공예찬진기암층,동시강화료니장성능조절화유호,가강찬압、전속、대빙량적감호조절등관리조시,순리완성료시공임무。원설계공심1300 m,실제종공심도1408 m,찬공만곡도2.9°,암심채취솔복개층평균고체80%,암층100%,광층100%,성공주기75천,원만완성료설계임무서요구,평위우질공。
The construction situation of Lujiatuo iron ore mine area is deep overburden layers in Quaternary and Tertiary systems, broken bedrock strata and accidents caused by collapse, sticking, diameter shrinkage and water leakage.The new special soil coring tool was selected for overburden layer drilling combined with conventional bit and special diamond bit;and wire-line core drilling technology was used for bedrock drilling with combination of enlarged borehole diameter, wall protection with high quality chemical grout and thief zone plugging.At the same time, mud performance adjustment and maintenance were strengthened, monitoring and adjusting of drilling pressure, drilling speed and pump amount were en-hanced.The original designed hole depth was 1300m and the actual depth is 1408m with borehole curvature of 2.9°, the average coring rate is up to 80%in overburden layer, 100%in both rock formation and ore bed, the hole completion cycle is 75 days.The requirements of the design program are met and the borehole is evaluated as high-quality one.