南京纬三路过江通道工程始发段具有覆盖土层薄、左右线间距小、始发进洞坡度大、曲线始发、始发井空间小等特点。通过相关工程经验比选,采用水泥搅拌桩加固和冻结加固,由于始发段不能在始发架上转弯,因而采用割线始发技术;始发进洞时,洞门密封钢环的密封方式与安装精度决定了始发阶段的密封效果,本文介绍了一种新型的洞门密封方式;由于始发井设计长度方向空间不够,将钢负环设计为常规管片的分块方式,采用管片拼装机进行拼装;针对南京纬三路工程地质情况,系统地介绍了始发泥水建压技术。采用以上关键技术,纬三路过江通道工程始发阶段盾构实际掘进姿态与设计姿态保持在规范允许范围内,始发架牢固可靠,钢负环拼装定位精确,密封钢环密封效果良好。
南京緯三路過江通道工程始髮段具有覆蓋土層薄、左右線間距小、始髮進洞坡度大、麯線始髮、始髮井空間小等特點。通過相關工程經驗比選,採用水泥攪拌樁加固和凍結加固,由于始髮段不能在始髮架上轉彎,因而採用割線始髮技術;始髮進洞時,洞門密封鋼環的密封方式與安裝精度決定瞭始髮階段的密封效果,本文介紹瞭一種新型的洞門密封方式;由于始髮井設計長度方嚮空間不夠,將鋼負環設計為常規管片的分塊方式,採用管片拼裝機進行拼裝;針對南京緯三路工程地質情況,繫統地介紹瞭始髮泥水建壓技術。採用以上關鍵技術,緯三路過江通道工程始髮階段盾構實際掘進姿態與設計姿態保持在規範允許範圍內,始髮架牢固可靠,鋼負環拼裝定位精確,密封鋼環密封效果良好。
남경위삼로과강통도공정시발단구유복개토층박、좌우선간거소、시발진동파도대、곡선시발、시발정공간소등특점。통과상관공정경험비선,채용수니교반장가고화동결가고,유우시발단불능재시발가상전만,인이채용할선시발기술;시발진동시,동문밀봉강배적밀봉방식여안장정도결정료시발계단적밀봉효과,본문개소료일충신형적동문밀봉방식;유우시발정설계장도방향공간불구,장강부배설계위상규관편적분괴방식,채용관편병장궤진행병장;침대남경위삼로공정지질정황,계통지개소료시발니수건압기술。채용이상관건기술,위삼로과강통도공정시발계단순구실제굴진자태여설계자태보지재규범윤허범위내,시발가뢰고가고,강부배병장정위정학,밀봉강배밀봉효과량호。
The shield launching section of Nanjing Weisanlu river-crossing tunnel has such features as shallow overburden, small spacing between the left tunnel tube and the right tunnel tube,large gradient,curved launching and small launching shaft.Cement mixing piles and freezing are adopted to reinforce the shield launching section.Because the shield cannot make a turn during launching,secant launching technology is adopted.Proper selection of launching soft eye seal structure and high seal structure installation accuracy provide excellent sealing for the shield launching.A new launching soft eye seal structure is introduced in this paper.The negative steel ring is designed in the form of normal segments and is assembled by the erector,because the longitudinal space of the launching shaft is not big enough to lift the negative ring. Besides,techniques for slurry pressure establishment,which are determined on basis of full consideration of the geology conditions,are systematically presented.By adopting the key technologies presented above,the slurry shield for Weisanlu river-crossing tunnel in Nanjing has bored through the launching section successfully,with the tunneling position of the slurry shield matching well with the design position,the reaction frame being solid and reliable,the steel negative rings having been positioned precisely and the sealing of the launching soft eye being in good condition.