岩石力学与工程学报
巖石力學與工程學報
암석역학여공정학보
CHINESE JOURNAL OF ROCK MECHANICS AND ENGINEERING
2015年
z1期
3328-3336
,共9页
余学义%王琦%赵兵朝%薄其山%王洪涛
餘學義%王琦%趙兵朝%薄其山%王洪濤
여학의%왕기%조병조%박기산%왕홍도
采矿工程%大采高%双巷布置%巷间煤柱%应力监测%采动影响
採礦工程%大採高%雙巷佈置%巷間煤柱%應力鑑測%採動影響
채광공정%대채고%쌍항포치%항간매주%응력감측%채동영향
mining engineering%large mining height%double roadways layout%pillar between roadways%stress monitoring%mining influence
巷间煤柱合理宽度的确定是确保大采高双巷布置工作面安全回采的关键。以亭南矿二盘区204大采高工作面双巷掘进运输顺槽和瓦斯抽放巷之间的煤柱为工程背景,首先通过现场应力监测的方法对巷间煤柱受双巷掘进及2次采动过程中的破坏规律进行了系统的研究,得出一次采动影响后靠近采空区侧煤柱的破坏区域宽度约为3 m;上位岩层低应力区域宽度约为18 m;一次采动后煤柱应力分布曲线呈不对称形态;二次采动影响后煤柱应力分布曲线呈不对称“马鞍状”,巷间煤柱边缘累计破碎宽度略大于9 m;同时对2次采动影响后煤柱的破坏区域进行了划分,初步确定巷间煤柱优化范围在5.2~13.0 m之间。其次采用数值模拟的方法分别研究了2次采动影响下宽度为4,6,8,10,12 m的5种不同尺寸巷间煤柱的应力演化规律、弹塑性区域变化规律和巷道变形规律,同时综合考虑安全生产、资源回收率等因素,最终确定大采高双巷布置工作面巷间煤柱的合理尺寸为10 m。最后通过工程实践验证了巷间煤柱留设的合理性。该研究结果可以为类似开采条件下巷间煤柱的留设提供参考。
巷間煤柱閤理寬度的確定是確保大採高雙巷佈置工作麵安全迴採的關鍵。以亭南礦二盤區204大採高工作麵雙巷掘進運輸順槽和瓦斯抽放巷之間的煤柱為工程揹景,首先通過現場應力鑑測的方法對巷間煤柱受雙巷掘進及2次採動過程中的破壞規律進行瞭繫統的研究,得齣一次採動影響後靠近採空區側煤柱的破壞區域寬度約為3 m;上位巖層低應力區域寬度約為18 m;一次採動後煤柱應力分佈麯線呈不對稱形態;二次採動影響後煤柱應力分佈麯線呈不對稱“馬鞍狀”,巷間煤柱邊緣纍計破碎寬度略大于9 m;同時對2次採動影響後煤柱的破壞區域進行瞭劃分,初步確定巷間煤柱優化範圍在5.2~13.0 m之間。其次採用數值模擬的方法分彆研究瞭2次採動影響下寬度為4,6,8,10,12 m的5種不同呎吋巷間煤柱的應力縯化規律、彈塑性區域變化規律和巷道變形規律,同時綜閤攷慮安全生產、資源迴收率等因素,最終確定大採高雙巷佈置工作麵巷間煤柱的閤理呎吋為10 m。最後通過工程實踐驗證瞭巷間煤柱留設的閤理性。該研究結果可以為類似開採條件下巷間煤柱的留設提供參攷。
항간매주합리관도적학정시학보대채고쌍항포치공작면안전회채적관건。이정남광이반구204대채고공작면쌍항굴진운수순조화와사추방항지간적매주위공정배경,수선통과현장응력감측적방법대항간매주수쌍항굴진급2차채동과정중적파배규률진행료계통적연구,득출일차채동영향후고근채공구측매주적파배구역관도약위3 m;상위암층저응력구역관도약위18 m;일차채동후매주응력분포곡선정불대칭형태;이차채동영향후매주응력분포곡선정불대칭“마안상”,항간매주변연루계파쇄관도략대우9 m;동시대2차채동영향후매주적파배구역진행료화분,초보학정항간매주우화범위재5.2~13.0 m지간。기차채용수치모의적방법분별연구료2차채동영향하관도위4,6,8,10,12 m적5충불동척촌항간매주적응력연화규률、탄소성구역변화규률화항도변형규률,동시종합고필안전생산、자원회수솔등인소,최종학정대채고쌍항포치공작면항간매주적합리척촌위10 m。최후통과공정실천험증료항간매주류설적합이성。해연구결과가이위유사개채조건하항간매주적류설제공삼고。
Determination of the reasonable width of pillars between roadways is the key for ensuring safety production of large mining height face with double roadways layout. Taking the double tunneling pillar between haulage gate and gas drainage roadway of 204 large mining height face in the second panel of Tingnan Coal Mine as the engineering background,firstly,the failure regularity of pillar between roadways under the effect of double tunneling and two times mining was systematically studied by using the method of field stress monitoring. A 3 m wide of fractured zone near the gob was found,and a 18 m wide low stress zone was realized. The distribution curve of stress in pillar between roadways after the first mining was asymmetric. After the second mining, distribution curve of stress in pillar between roadways was like a asymmetric“saddle”and the cumulative broken at the edge of pillar was more than 9 m. at the same time,the division of pillar between roadways was given after the two times mining,and the reasonable width of pillar between roadways was determined preliminarily to be 5.2—13.0 m. Secondly,the stress evolution law,the elastic-plastic region variation,and the roadways deformation law of 5 different coal pillar that width of 4 m,6 m,8 m,10 m and 12 m were studied by numerical simulation. Various elements such as safety production and resources recovery were considered comprehensively. The reasonable width of double tunneling pillar between roadways in large mining height face was 10m. Finally,the reasonableness of the pillar width was verified by engineering practice. The results can provide a reference for the setting of pillar between roadways with similar mining conditions.