判定水下灌注桩是否出现基桩缺陷,应对桩身进行复合检测。该文依据工程自身特点,参照相应规范要求,分析影响结构安全的缺陷成因,判定出桩身缺陷的具体部位,因地制宜地制定出相应的加固处理方法,能有效节约处理工期和加固处理成本。
判定水下灌註樁是否齣現基樁缺陷,應對樁身進行複閤檢測。該文依據工程自身特點,參照相應規範要求,分析影響結構安全的缺陷成因,判定齣樁身缺陷的具體部位,因地製宜地製定齣相應的加固處理方法,能有效節約處理工期和加固處理成本。
판정수하관주장시부출현기장결함,응대장신진행복합검측。해문의거공정자신특점,삼조상응규범요구,분석영향결구안전적결함성인,판정출장신결함적구체부위,인지제의지제정출상응적가고처리방법,능유효절약처리공기화가고처리성본。
The body of the underwater cast-in-pace pile should be compositely tested to judge whether pile defect will occur. Based on the features of the project and related regulations for reference, the defect causes concerning structural safety are analyzed, the specific part of the defect is located and relat-ed reinforcement treatment method is come up with accordingly. Thus the time limit of the project and the reinforcement treatment capital can both be effectively saved.