金属矿山
金屬礦山
금속광산
METAL MINE
2015年
4期
142-145
,共4页
采动%桥墩%桥台%移动与变形%维修%加固
採動%橋墩%橋檯%移動與變形%維脩%加固
채동%교돈%교태%이동여변형%유수%가고
Mining influence%Bridge pier%Bridge abutment%Movement and deformation%Maintenance%Strengthening
为了实现受采动影响铁路桥梁的安全运行,应用概率积分法预计了S2 S7工作面开采对三连铁路桥产生的最大移动与变形值。在此基础上分析了下沉、倾斜及水平变形对桥梁结构的影响。结果表明:桥梁下沉后铁路桥下过水断面净空高度满足规范要求;桥梁纵向倾斜不影响行车,可通过不断调整轨面来满足规范要求的桥梁横向倾斜且不影响墩台的稳定性;桥梁纵向压缩不会影响正常使用,但桥梁基础横向拉伸变形已达Ⅲ级。针对桥梁基础有可能遭受到较大损害的情况,提出了采用扁钢对桥墩及桥台进行加固的设计方案,并提出了保证线路正常运行的安全措施。实践表明,经过加固的铁路桥经受住了S2 S7工作面的采动影响,达到了铁路桥下安全采煤的目的。
為瞭實現受採動影響鐵路橋樑的安全運行,應用概率積分法預計瞭S2 S7工作麵開採對三連鐵路橋產生的最大移動與變形值。在此基礎上分析瞭下沉、傾斜及水平變形對橋樑結構的影響。結果錶明:橋樑下沉後鐵路橋下過水斷麵淨空高度滿足規範要求;橋樑縱嚮傾斜不影響行車,可通過不斷調整軌麵來滿足規範要求的橋樑橫嚮傾斜且不影響墩檯的穩定性;橋樑縱嚮壓縮不會影響正常使用,但橋樑基礎橫嚮拉伸變形已達Ⅲ級。針對橋樑基礎有可能遭受到較大損害的情況,提齣瞭採用扁鋼對橋墩及橋檯進行加固的設計方案,併提齣瞭保證線路正常運行的安全措施。實踐錶明,經過加固的鐵路橋經受住瞭S2 S7工作麵的採動影響,達到瞭鐵路橋下安全採煤的目的。
위료실현수채동영향철로교량적안전운행,응용개솔적분법예계료S2 S7공작면개채대삼련철로교산생적최대이동여변형치。재차기출상분석료하침、경사급수평변형대교량결구적영향。결과표명:교량하침후철로교하과수단면정공고도만족규범요구;교량종향경사불영향행차,가통과불단조정궤면래만족규범요구적교량횡향경사차불영향돈태적은정성;교량종향압축불회영향정상사용,단교량기출횡향랍신변형이체Ⅲ급。침대교량기출유가능조수도교대손해적정황,제출료채용편강대교돈급교태진행가고적설계방안,병제출료보증선로정상운행적안전조시。실천표명,경과가고적철로교경수주료S2 S7공작면적채동영향,체도료철로교하안전채매적목적。
In order to realize the safety service of the railway bridge influenced by mining,the probability integral method was used to predict the movement and deformation values of the Sanlian railway bridge at the S2 S7 working face during mining. Based on this,the effect of subsidence,inclination and horizontal deformation on structure of railway bridge was analyzed. The results showed that the wetted cross section height under the railway bridge is in accord with the requirement of criterion,the longitudinal inclination of the bridge beam did not influence the driving,and the horizontal inclination met the requirement of the criterion by adjusting the orbit plane,so it cannot influence the stability of the bridge pier. The longitudinal compression of the bridge did not affect the use, but the tensile deformation of the bridge lateral basis reached Class III, resulting that the bridge foundation may suffer the great damage. In view of this,the design which adopted the flat steel to strengthen the bridge pier and abutment was proposed,and the safety measures for the normal service of the bridge were put forward. The practice showed that the strengthened railway bridge can bear the mining influence of S2 S7 working face,to achieve the safety coal min-ing under railway bridge.