隧道建设
隧道建設
수도건설
TUNNEL CONSTRUCTION
2015年
4期
316-321
,共6页
瘦西湖隧道%大直径曲线盾构%地表沉降%分层沉降%水平位移
瘦西湖隧道%大直徑麯線盾構%地錶沉降%分層沉降%水平位移
수서호수도%대직경곡선순구%지표침강%분층침강%수평위이
Slender West Lake Crossing Tunnel%curved tunnel bored by large-diameter shield%ground surface settlement%layered settlement%horizontal displacement
大直径曲线盾构隧道中,盾构掘进时盾构对其两侧和拱顶上方的土体作用不同,不同位置土体表现出不同的变形规律。为了保证曲线盾构隧道施工安全进行,并针对变形的差异性提出相应的解决方案,采用现场监测和 FLAC 3D 数值模拟相结合的方法,对超大直径曲线盾构隧道施工中周边土体变形进行分析,监测项目包括地表沉降、分层沉降、土体深层水平位移。研究结果表明:1)随着隧道掘进,地表沉降呈现反“S”形变形趋势,与3个变形阶段对应,即盾构切口到达时缓慢隆沉,盾构通过时沉降较快,盾尾脱出时沉降趋于稳定;2)横向沉降槽曲线中,掘进时隧道掘进方向曲线内侧沉降量比外侧对称位置沉降更大;3)土体水平位移在隧道掘进方向曲线内侧变形量小于外侧变形量。
大直徑麯線盾構隧道中,盾構掘進時盾構對其兩側和拱頂上方的土體作用不同,不同位置土體錶現齣不同的變形規律。為瞭保證麯線盾構隧道施工安全進行,併針對變形的差異性提齣相應的解決方案,採用現場鑑測和 FLAC 3D 數值模擬相結閤的方法,對超大直徑麯線盾構隧道施工中週邊土體變形進行分析,鑑測項目包括地錶沉降、分層沉降、土體深層水平位移。研究結果錶明:1)隨著隧道掘進,地錶沉降呈現反“S”形變形趨勢,與3箇變形階段對應,即盾構切口到達時緩慢隆沉,盾構通過時沉降較快,盾尾脫齣時沉降趨于穩定;2)橫嚮沉降槽麯線中,掘進時隧道掘進方嚮麯線內側沉降量比外側對稱位置沉降更大;3)土體水平位移在隧道掘進方嚮麯線內側變形量小于外側變形量。
대직경곡선순구수도중,순구굴진시순구대기량측화공정상방적토체작용불동,불동위치토체표현출불동적변형규률。위료보증곡선순구수도시공안전진행,병침대변형적차이성제출상응적해결방안,채용현장감측화 FLAC 3D 수치모의상결합적방법,대초대직경곡선순구수도시공중주변토체변형진행분석,감측항목포괄지표침강、분층침강、토체심층수평위이。연구결과표명:1)수착수도굴진,지표침강정현반“S”형변형추세,여3개변형계단대응,즉순구절구도체시완만륭침,순구통과시침강교쾌,순미탈출시침강추우은정;2)횡향침강조곡선중,굴진시수도굴진방향곡선내측침강량비외측대칭위치침강경대;3)토체수평위이재수도굴진방향곡선내측변형량소우외측변형량。
The surrounding ground will be disturbed when a large diameter shield bores in curved section.In the paper, analysis is made on the influence of a super-large diameter shield tunneling on the surrounding environment by means of site monitoring and FLAC 3D numerical simulation,so as to guarantee the safety of the construction and to provide a solution for the deformation difference.The monitoring items include ground surface settlement,layered settlement and deep horizontal displacement of soil.The study results show that:1 )The ground surface settlement takes place in 3 stages,i.e.,when the cutting ring of the shield reaches,the rate of the ground surface settlement is low;when the shield passes,the rate of the ground surface settlement is high;when the shield tail passes,the rate of the ground surface settlement becomes stable;2)The ground surface settlement on the inner side of the curved tunnel section is larger than that on the outer side of the curved tunnel section;3)The horizontal displacement of ground on the inner side of the curved tunnel section is smaller than that on the outer side of the curved tunnel section.