铁路隧道%富水宽张裂隙带%注浆%带水作业%施工
鐵路隧道%富水寬張裂隙帶%註漿%帶水作業%施工
철로수도%부수관장렬극대%주장%대수작업%시공
Railway tunnel%Water rich and wide tension fissure zone%Grouting%Work in presence of water%Construction
太行山隧道施工中遇到富水宽张裂隙带,左线长度218 m、右线长度200 m,超前探孔单孔最大涌水量230 m3/h,静水压力0.8 MPa,围岩为Ⅲ级石英砂岩。施工中先后采取全断面帷幕注浆、带水作业、周边注浆等方法。工程实践表明:(1)3种方法均可以满足开挖要求,施工进度分别为25、20、39 m/月,周边注浆处理该类地层更有优势;(2)带水作业必须满足超前探孔单孔出水量小于40 m3/h、总涌水量小于300 m3/h、破碎裂隙段长度小于3 m的要求,否则,施工安全和进度无法保证;(3)周边注浆与全断面帷幕注浆相比,注浆孔数量减少59%,注浆时间缩短56%,进度提高56%;(4)全断面帷幕注浆采用2 L/min/m作为检查孔出水量标准是合适的,并可适度放宽,周边注浆可采用5 L/min/m的标准。
太行山隧道施工中遇到富水寬張裂隙帶,左線長度218 m、右線長度200 m,超前探孔單孔最大湧水量230 m3/h,靜水壓力0.8 MPa,圍巖為Ⅲ級石英砂巖。施工中先後採取全斷麵帷幕註漿、帶水作業、週邊註漿等方法。工程實踐錶明:(1)3種方法均可以滿足開挖要求,施工進度分彆為25、20、39 m/月,週邊註漿處理該類地層更有優勢;(2)帶水作業必鬚滿足超前探孔單孔齣水量小于40 m3/h、總湧水量小于300 m3/h、破碎裂隙段長度小于3 m的要求,否則,施工安全和進度無法保證;(3)週邊註漿與全斷麵帷幕註漿相比,註漿孔數量減少59%,註漿時間縮短56%,進度提高56%;(4)全斷麵帷幕註漿採用2 L/min/m作為檢查孔齣水量標準是閤適的,併可適度放寬,週邊註漿可採用5 L/min/m的標準。
태행산수도시공중우도부수관장렬극대,좌선장도218 m、우선장도200 m,초전탐공단공최대용수량230 m3/h,정수압력0.8 MPa,위암위Ⅲ급석영사암。시공중선후채취전단면유막주장、대수작업、주변주장등방법。공정실천표명:(1)3충방법균가이만족개알요구,시공진도분별위25、20、39 m/월,주변주장처리해류지층경유우세;(2)대수작업필수만족초전탐공단공출수량소우40 m3/h、총용수량소우300 m3/h、파쇄렬극단장도소우3 m적요구,부칙,시공안전화진도무법보증;(3)주변주장여전단면유막주장상비,주장공수량감소59%,주장시간축단56%,진도제고56%;(4)전단면유막주장채용2 L/min/m작위검사공출수량표준시합괄적,병가괄도방관,주변주장가채용5 L/min/m적표준。
The construction of Taihangshan tunnel is encountered in water rich and wide tension fissure zone with left line length 218 m and right line length 200 m. The maximum gushing water is predicted to be 230 m3/h and the static water pressure 0. 8 MPa. The surrounding rock is grade quartz sandstone. It is constructed with full face curtain grouting in presence of water and with peripheral grouting method. Engineering practices show that: ( 1 ) the three methods can meet the requirements for excavation with construction progress 25 m/month, 20 m/month and 39m/month respectively, the peripheral grouting treatment of the formation is very advantageous;(2) construction with presence of water must satisfy the requirements for advanced hole drilling single hole water less than 40 m3/h, the total water amount less than 300 m3/h and crack length less than 3 m, otherwise, the construction safety and schedule cannot be guaranteed; ( 3 ) compared with surrounding grouting and full face curtain grouting, grouting hole is reduced by 59%, grouting time cut by 56%, schedule increased by 56%; ( 4 ) the entire cross-section curtain grouting by using 2 L/min/m as the inspection hole water volume standard is appropriate, and may be extended and 5L/min/m standard may be applied for peripheral grouting.