大倾角%大断面%下山%施工管理
大傾角%大斷麵%下山%施工管理
대경각%대단면%하산%시공관리
large dip angle%large section%downhill%construction management
一采区回风上山是矿井建设的主矛盾线工程,施工过程中现场通过创新实施后部排矸连续化、辅助运输便捷化等8项管理措施,克服了大断面、大倾角下山施工的诸多不利因素,提前120d完成了工程施工任务,为提前3个月实现主、副、风井贯通明风奠定了坚实基础。
一採區迴風上山是礦井建設的主矛盾線工程,施工過程中現場通過創新實施後部排矸連續化、輔助運輸便捷化等8項管理措施,剋服瞭大斷麵、大傾角下山施工的諸多不利因素,提前120d完成瞭工程施工任務,為提前3箇月實現主、副、風井貫通明風奠定瞭堅實基礎。
일채구회풍상산시광정건설적주모순선공정,시공과정중현장통과창신실시후부배안련속화、보조운수편첩화등8항관리조시,극복료대단면、대경각하산시공적제다불리인소,제전120d완성료공정시공임무,위제전3개월실현주、부、풍정관통명풍전정료견실기출。
one mining area return air is the main contradiction of the line project of mine construction, during constructing ,using the continuous transportation gangue in tail, the convenient auxiliary transport and other 8 management measures, overcome the disadvantages of large section and steep downhill construction, completed 120 days ahead of construction tasks, laid a solid foundation for the 3 months ahead of schedule to achieve the main and auxiliary shaft, through the wind.