阐述了山西中阳钢铁厂棒材车间收集区域主体钢结构的施工方法,给出了钢铁厂棒材车间的收集区域选择,吊机占位及主吊机的选择,提出了钢柱的吊装、找正以及吊车梁安装的方法,并对屋面结构进行了安装,该钢结构流程可以为类似工程提供参考。
闡述瞭山西中暘鋼鐵廠棒材車間收集區域主體鋼結構的施工方法,給齣瞭鋼鐵廠棒材車間的收集區域選擇,弔機佔位及主弔機的選擇,提齣瞭鋼柱的弔裝、找正以及弔車樑安裝的方法,併對屋麵結構進行瞭安裝,該鋼結構流程可以為類似工程提供參攷。
천술료산서중양강철엄봉재차간수집구역주체강결구적시공방법,급출료강철엄봉재차간적수집구역선택,조궤점위급주조궤적선택,제출료강주적조장、조정이급조차량안장적방법,병대옥면결구진행료안장,해강결구류정가이위유사공정제공삼고。
This paper has described the construction method of the main steel structure in the bar shop of Zhongyang Shanxi iron and steel factory, and the collection area selection of bar shop in iron and steel plant is given. This paper has given a description of the crane occupancy and the choice of the main hoist. This paper has given the hoisting of the steel column and the installation of the crane beam,and the roof structure instal-lation. The steel structure process can provide reference for similar projects.