广西水利水电
廣西水利水電
엄서수이수전
GX WATER RESOURCES & HYDROPOWER ENGINEERING
2015年
3期
19-20,23
,共3页
混凝土面板坝%趾板%强风化层%趾板基础%防渗
混凝土麵闆壩%趾闆%彊風化層%趾闆基礎%防滲
혼응토면판패%지판%강풍화층%지판기출%방삼
Concrete face-slab dam%toe slab%intensely weathered layer%toe slab foundation%seepage prevention
根据DXS水库面板坝基础工程地质条件,对平趾板与斜趾板两种布置形式进行比较,为减少开挖量,降低上游的高边坡,采用斜趾板与延长防渗板的布置型式。并结合工程实际简要介绍了该面板坝趾板设计要点。工程投运3年多,面板坝趾板混凝土质量良好,趾板无裂缝,水库无渗漏,大坝运行正常。
根據DXS水庫麵闆壩基礎工程地質條件,對平趾闆與斜趾闆兩種佈置形式進行比較,為減少開挖量,降低上遊的高邊坡,採用斜趾闆與延長防滲闆的佈置型式。併結閤工程實際簡要介紹瞭該麵闆壩趾闆設計要點。工程投運3年多,麵闆壩趾闆混凝土質量良好,趾闆無裂縫,水庫無滲漏,大壩運行正常。
근거DXS수고면판패기출공정지질조건,대평지판여사지판량충포치형식진행비교,위감소개알량,강저상유적고변파,채용사지판여연장방삼판적포치형식。병결합공정실제간요개소료해면판패지판설계요점。공정투운3년다,면판패지판혼응토질량량호,지판무렬봉,수고무삼루,대패운행정상。
For the concrete face-slab dam of DXS Reservoir, two alternatives of flat toe slab and oblique slab were compared combined with the foundation engineering geological conditions, and the oblique toe slab alternative with extended anti-seepage slab was adopted due to less excavation quantity and lower upstream bank slope. A brief in?troduction was made on the key points of toe slab design combined with the actual conditions of the project. The project has been operating normally for more than 3 years, showing good concrete quality, without crack at toe slab or reservoir seepage.