TECHNIQUE OF SEEPAGE CONTROL
2015年
3期
24-28
,共5页
赵升峰%马世强%黄广龙%章新%周文苑
趙升峰%馬世彊%黃廣龍%章新%週文苑
조승봉%마세강%황엄룡%장신%주문원
超挖%基坑倾覆%支护桩内力%变形
超挖%基坑傾覆%支護樁內力%變形
초알%기갱경복%지호장내력%변형
over excavation%overturning of foundation pit%internal forces of supporting piles%deformation
南京浦口某典型软土基坑,采用悬臂钻孔灌注桩结合坑外双轴水泥土搅拌桩止水帷幕的支护型式。基坑开挖前支护桩已施工,但后期建筑结构进行了调整,使得基坑加深1.0 m 。由于抢工期,未进行基坑加固便开始挖土,开挖过程也未采取分段开挖,导致支护桩倾覆,基坑出现险情,坑边路面下沉、坍塌。通过对比原设计与实际开挖2种条件下土压力、支护桩的内力、基坑变形及地面沉降的变化,阐述了险情产生的原因。根据现场情况提出了处理措施,保证基坑的后续施工,同时给出了类似基坑工程的设计、施工和管理方面引以为鉴的建议。
南京浦口某典型軟土基坑,採用懸臂鑽孔灌註樁結閤坑外雙軸水泥土攪拌樁止水帷幕的支護型式。基坑開挖前支護樁已施工,但後期建築結構進行瞭調整,使得基坑加深1.0 m 。由于搶工期,未進行基坑加固便開始挖土,開挖過程也未採取分段開挖,導緻支護樁傾覆,基坑齣現險情,坑邊路麵下沉、坍塌。通過對比原設計與實際開挖2種條件下土壓力、支護樁的內力、基坑變形及地麵沉降的變化,闡述瞭險情產生的原因。根據現場情況提齣瞭處理措施,保證基坑的後續施工,同時給齣瞭類似基坑工程的設計、施工和管理方麵引以為鑒的建議。
남경포구모전형연토기갱,채용현비찬공관주장결합갱외쌍축수니토교반장지수유막적지호형식。기갱개알전지호장이시공,단후기건축결구진행료조정,사득기갱가심1.0 m 。유우창공기,미진행기갱가고편개시알토,개알과정야미채취분단개알,도치지호장경복,기갱출현험정,갱변로면하침、담탑。통과대비원설계여실제개알2충조건하토압력、지호장적내력、기갱변형급지면침강적변화,천술료험정산생적원인。근거현장정황제출료처리조시,보증기갱적후속시공,동시급출료유사기갱공정적설계、시공화관리방면인이위감적건의。
The supporting structure of a typical soft clay foundation pit in Pukou ,Nanjing is consist of cast-in-place bored piles constructed by using cantilevers and the impermeable curtain made of biaxial soil-cement piles outside of the pit .The construction of the supporting piles had been completed before the excavation .However ,the subsequent con-struction was adjusted which added 1 m to the depth of the foundation pit .Meanwhile ,due to the rushing of the construc-tion ,the supporting structure of the pit was not reinforced before the excavation ,and excavation process was not con-structed by stagess .These misconducts led to the overturning of the supporting structure ,as well as the settlement and subsidence of the road surface around the pit .According to the comparison of the soil pressure ,the internal force of the supporting piles ,the deformation of the foundation pit and the ground settlement in the original design and the actual ex-cavation ,the causes of the dangerous circumstances were explained and analyzed .The treatment measures were proposed for the subsequent construction of the pit based on the situation ,meanwhile the suggestion about design ,construction and management of the similar foundation pits were put forward for future references .