中国港湾建设
中國港灣建設
중국항만건설
CHINA HARBOUR ENGINEERING
2015年
7期
105-109
,共5页
沉管%裂缝%顶推%安全%管节水平姿态%保障措施
沉管%裂縫%頂推%安全%管節水平姿態%保障措施
침관%렬봉%정추%안전%관절수평자태%보장조시
immersed tube%cracks%pushing%safety%horizontal attitude of tube%safeguard measures
以岛隧工程沉管预制厂顶推施工为例,论述沉管顶推施工的技术保障措施。港珠澳大桥岛隧工程超大型沉管的顶推施工是一项全新的科技创新工艺,其设计、基础施工、顶推过程等每个环节都必须认真研究,谨慎实施,做好技术保障。
以島隧工程沉管預製廠頂推施工為例,論述沉管頂推施工的技術保障措施。港珠澳大橋島隧工程超大型沉管的頂推施工是一項全新的科技創新工藝,其設計、基礎施工、頂推過程等每箇環節都必鬚認真研究,謹慎實施,做好技術保障。
이도수공정침관예제엄정추시공위례,논술침관정추시공적기술보장조시。항주오대교도수공정초대형침관적정추시공시일항전신적과기창신공예,기설계、기출시공、정추과정등매개배절도필수인진연구,근신실시,주호기술보장。
Based on the pushing construction of the immersed tube prefabricated factory in the island and tunnel project, we discussed the technical safeguard measures of immersed tube pushing. The pushing construction of super large immersed tube in the island&tunnel project of Hongkong-Zhuhai-Macao Bridge is new technical innovation process. The design, foundation construction and pushing process must be taken seriously, each link must be carefully studied and implemented, and do well in technical support.