港珠澳大桥%现浇箱梁%新型模板体系%变截面箱梁%木工字梁
港珠澳大橋%現澆箱樑%新型模闆體繫%變截麵箱樑%木工字樑
항주오대교%현요상량%신형모판체계%변절면상량%목공자량
Hongkong-Zhuhai-Macao Bridge%cast-in-situ box girder%new type of formwork system%box girder with varied section%wooden I-beam
港珠澳大桥东人工岛岛桥结合部非通航孔桥现浇箱梁施工属于海上作业,安全风险高,箱梁曲线弧度大,施工要求高,工期短,难度大。通过采用新型模板体系,显著提高了现浇箱梁的施工进度、质量和安全,可为类似工程参考。
港珠澳大橋東人工島島橋結閤部非通航孔橋現澆箱樑施工屬于海上作業,安全風險高,箱樑麯線弧度大,施工要求高,工期短,難度大。通過採用新型模闆體繫,顯著提高瞭現澆箱樑的施工進度、質量和安全,可為類似工程參攷。
항주오대교동인공도도교결합부비통항공교현요상량시공속우해상작업,안전풍험고,상량곡선호도대,시공요구고,공기단,난도대。통과채용신형모판체계,현저제고료현요상량적시공진도、질량화안전,가위유사공정삼고。
The cast-in-situ box girder construction of non navigable span, which is in the joint part of island and bridge on the east island of Hongkong-Zhuhai-Macao Bridge, is operated in marine, with high security risk. The curve of the box girder is large, and the construction has high requirements, short period, and huge difficulty. The adoption of new type of formwork technology has significantly enhanced the construction schedule, quality and safety of the cast-in-situ box girder. The paper can supply references for the similar projects.