YANGTZE RIVER
2015年
15期
26-29
,共4页
郭红亮%石运深%焦雨佳%李苗%胡敏
郭紅亮%石運深%焦雨佳%李苗%鬍敏
곽홍량%석운심%초우가%리묘%호민
搅拌桩%泄水闸%粉细砂%液化%格栅%兴隆水利枢纽
攪拌樁%洩水閘%粉細砂%液化%格柵%興隆水利樞紐
교반장%설수갑%분세사%액화%격책%흥륭수리추뉴
mixing pile%discharge sluice%fine sand%liquefaction%grid%Xinlong Hydrojunction Projec
汉江兴隆水利枢纽泄水闸深厚粉细砂土层地基厚约25 m。为解决地基沉降量大与饱和砂土震动液化问题,经对强夯法、振冲法和水泥土搅拌桩法等处理方案比选后,决定采用水泥土搅拌桩对地基进行处理。现有搅拌桩工程实例大多是处理摩阻力较小的黏性软土,对于处理摩阻力大和存在流动地下水的粉细砂层尚属少见。为此,对水泥土搅拌桩进行了室内和现场试验研究,证实了搅拌桩适宜于处理兴隆泄水闸粉细砂地基。搅拌桩采取格栅式布置,置换率约20%。施工完成后的搅拌桩质量检测全部合格,变形监测结果表明,沉降量控制满足设计要求。
漢江興隆水利樞紐洩水閘深厚粉細砂土層地基厚約25 m。為解決地基沉降量大與飽和砂土震動液化問題,經對彊夯法、振遲法和水泥土攪拌樁法等處理方案比選後,決定採用水泥土攪拌樁對地基進行處理。現有攪拌樁工程實例大多是處理摩阻力較小的黏性軟土,對于處理摩阻力大和存在流動地下水的粉細砂層尚屬少見。為此,對水泥土攪拌樁進行瞭室內和現場試驗研究,證實瞭攪拌樁適宜于處理興隆洩水閘粉細砂地基。攪拌樁採取格柵式佈置,置換率約20%。施工完成後的攪拌樁質量檢測全部閤格,變形鑑測結果錶明,沉降量控製滿足設計要求。
한강흥륭수리추뉴설수갑심후분세사토층지기후약25 m。위해결지기침강량대여포화사토진동액화문제,경대강항법、진충법화수니토교반장법등처리방안비선후,결정채용수니토교반장대지기진행처리。현유교반장공정실례대다시처리마조력교소적점성연토,대우처리마조력대화존재류동지하수적분세사층상속소견。위차,대수니토교반장진행료실내화현장시험연구,증실료교반장괄의우처리흥륭설수갑분세사지기。교반장채취격책식포치,치환솔약20%。시공완성후적교반장질량검측전부합격,변형감측결과표명,침강량공제만족설계요구。
The thickness of the sluice foundation of Xinglong Hydrojunction Project on Hanjiang River, a deep fine sand layer, is 25 m. To solve the liquefaction problem of saturated sand and large settlement of the foundation, the foundation was treated by using cement-soil mixing pile rather than the dynamic consolidation or vibroflotation method through comparison. In the current cases of mixing pile, the viscous soft soil with small frictional resistance are treated; however, the treatment of fine sand layer with large frictional resistance and running groundwater are rare. Therefore, the laboratory experiment and in-situ test of cement-soil mixing pile was conducted, which proved that this mixing pile is suitable for the treatment of the sluice foundation of Xin-glong Hydrojunction Project. The piles are arranged in grid with the replacement rate of 20%. The quality of the mixing pile meets the requirement and the deformation monitoring shows that the settlement control meets the design requirement.