2015年
17期
4326-4334
,共9页
王嘉阳%程春田%廖胜利%汪明清%苏华英
王嘉暘%程春田%廖勝利%汪明清%囌華英
왕가양%정춘전%료성리%왕명청%소화영
梯级水电%实时%机组限制区%日前计划%出力平稳性%弃水
梯級水電%實時%機組限製區%日前計劃%齣力平穩性%棄水
제급수전%실시%궤조한제구%일전계화%출력평은성%기수
hydro cascaded system%real-time%unit’s restricted zones%day-ahead scheduling%generation smoothness constraint%surplus water
由于负荷预测偏差、径流预报不准确,如何快速、可靠地调整发电计划是梯级水电群实时调度中的难点和关键问题,主要体现在快速躲避机组限制区、兼顾电站日前计划和出力平稳性、最小化电站弃水等3个方面。针对上述问题,提出复杂约束限制下的梯级水电站群实时优化调度方法及调整策略,包括电站计算序位确定、电站组合确定、负荷偏差光滑处理、厂间负荷偏差分配和弃水调整策略。引入负荷偏差光滑技术,重构负荷偏差,保证厂间负荷偏差满足出力平稳性要求;在厂间负荷偏差分配过程中,协调日前计划,动态调整电站出力,避免落入机组限制区;采用弃水修正策略,沿约束边界调整电站出力,实现预泄腾库。所提方法和策略,能够充分考虑日前发电计划指导性,避免电站出力频繁波动,保证机组实时躲避限制区运行,避免不必要弃水发生。贵州电网乌江流域梯级水电站群厂网协调实际过程模拟分析表明,所提方法和策略能够快速可靠地满足实际工程要求,是一种是切实可行的方法和策略。
由于負荷預測偏差、徑流預報不準確,如何快速、可靠地調整髮電計劃是梯級水電群實時調度中的難點和關鍵問題,主要體現在快速躲避機組限製區、兼顧電站日前計劃和齣力平穩性、最小化電站棄水等3箇方麵。針對上述問題,提齣複雜約束限製下的梯級水電站群實時優化調度方法及調整策略,包括電站計算序位確定、電站組閤確定、負荷偏差光滑處理、廠間負荷偏差分配和棄水調整策略。引入負荷偏差光滑技術,重構負荷偏差,保證廠間負荷偏差滿足齣力平穩性要求;在廠間負荷偏差分配過程中,協調日前計劃,動態調整電站齣力,避免落入機組限製區;採用棄水脩正策略,沿約束邊界調整電站齣力,實現預洩騰庫。所提方法和策略,能夠充分攷慮日前髮電計劃指導性,避免電站齣力頻繁波動,保證機組實時躲避限製區運行,避免不必要棄水髮生。貴州電網烏江流域梯級水電站群廠網協調實際過程模擬分析錶明,所提方法和策略能夠快速可靠地滿足實際工程要求,是一種是切實可行的方法和策略。
유우부하예측편차、경류예보불준학,여하쾌속、가고지조정발전계화시제급수전군실시조도중적난점화관건문제,주요체현재쾌속타피궤조한제구、겸고전참일전계화화출력평은성、최소화전참기수등3개방면。침대상술문제,제출복잡약속한제하적제급수전참군실시우화조도방법급조정책략,포괄전참계산서위학정、전참조합학정、부하편차광활처리、엄간부하편차분배화기수조정책략。인입부하편차광활기술,중구부하편차,보증엄간부하편차만족출력평은성요구;재엄간부하편차분배과정중,협조일전계화,동태조정전참출력,피면락입궤조한제구;채용기수수정책략,연약속변계조정전참출력,실현예설등고。소제방법화책략,능구충분고필일전발전계화지도성,피면전참출력빈번파동,보증궤조실시타피한제구운행,피면불필요기수발생。귀주전망오강류역제급수전참군엄망협조실제과정모의분석표명,소제방법화책략능구쾌속가고지만족실제공정요구,시일충시절실가행적방법화책략。
The key problem of real-time scheduling of hydro cascaded system is how to fast and reliably adjust day-ahead scheduling according to deviation of load forecasting and runoff prediction. It encounters three primary difficulties: avoidance of unit’s restricted zones, consideration of day-ahead scheduling and generation smoothness, and minimization of surplus water. This paper presented a real-time scheduling method and strategy for hydro cascaded system with complex constraints, including processes of computation order decision, plant commitment strategy, load deviation smoothing, load deviation dispatch and surplus water adjustment strategy. Load deviation smoothing process is adopted to shape load deviation to ensure generation smoothness constraint satisfied. In the process of load deviation dispatch among plants, plants’ generation is modified dynamically based on day-ahead scheduling, and unit’s restricted zones can be rapidly avoided. Simultaneously, an adjustment strategy for preventing surplus water is adopted to achieve pre-discharge by revising plants’ generation along constraint boundary. The proposed method and strategy can implement the following effects: full coordination with day-ahead scheduling, prevent of frequent fluctuation of plants’ generation, avoidance of unit’s restricted zones, and surplus water prevention. Two case studies on Wujiang mainstream cascaded hydropower plants oriented to the coordination of power plants and power grid is used to test the proposed method and strategy, and shows that it is feasible and can meet actual operation demands.