山西电力
山西電力
산서전력
SHANXI ELECTRIC POWER
2015年
4期
49-51
,共3页
智能变电站%合并单元%继电保护%传输延时
智能變電站%閤併單元%繼電保護%傳輸延時
지능변전참%합병단원%계전보호%전수연시
smart substation%merging unit%relay protection%transmission delay
分析了智能变电站合并单元采样同步和延时产生原因,通过现场实际案例及现场应用,验证单元采样同步和延时对保护装置的影响,进一步得出智能站采集系统的综合误差,对智能变电站合并单元的设计、制造、测试和运行中的检查提出方法和建议。
分析瞭智能變電站閤併單元採樣同步和延時產生原因,通過現場實際案例及現場應用,驗證單元採樣同步和延時對保護裝置的影響,進一步得齣智能站採集繫統的綜閤誤差,對智能變電站閤併單元的設計、製造、測試和運行中的檢查提齣方法和建議。
분석료지능변전참합병단원채양동보화연시산생원인,통과현장실제안례급현장응용,험증단원채양동보화연시대보호장치적영향,진일보득출지능참채집계통적종합오차,대지능변전참합병단원적설계、제조、측시화운행중적검사제출방법화건의。
This article analyzed the causes of intelligent substation merging unit sampling synchronization or time delay. The effects of sampling synchronization or time delay on protective device were verified through practical case and field application, and the comprehensive errors of the collecting system were reached. It also puts forward methods and suggestions for the design, production, testing and operation of merging unit in smart station.