郑州新郑国际机场T2航站楼建筑面积48?45万m2,航站楼?~?轴下穿有城际铁路、地铁通过,该区域简称共建区。两者工期均较为紧张,需在非外界因素干扰下施工,且城铁上部为航站楼行李系统控制中心占地区域,传统的先深后浅施工安排无法满足总进度需要。经过多次设计优化和研讨,确定了城际铁路盖挖施工整体思路,即共建区上部设计54m长转换大梁,既满足下部通车空间需要,又可将跨度范围内航站楼荷载通过转换梁传至地下承台,梁上部铺设贝雷架操作平台,既充当共建区航站楼1层主体结构满堂架支撑系统,又为下部城际铁路施工创造封闭、安全的盖挖环境,确保两者能同步施工。该联合施工方案在确保施工安全、解决垂直运输、缩短工期方面进行了积极探索,为新郑国际机场T2航站楼缩短总工期180d以上,创造了较大的经济和社会效益。
鄭州新鄭國際機場T2航站樓建築麵積48?45萬m2,航站樓?~?軸下穿有城際鐵路、地鐵通過,該區域簡稱共建區。兩者工期均較為緊張,需在非外界因素榦擾下施工,且城鐵上部為航站樓行李繫統控製中心佔地區域,傳統的先深後淺施工安排無法滿足總進度需要。經過多次設計優化和研討,確定瞭城際鐵路蓋挖施工整體思路,即共建區上部設計54m長轉換大樑,既滿足下部通車空間需要,又可將跨度範圍內航站樓荷載通過轉換樑傳至地下承檯,樑上部鋪設貝雷架操作平檯,既充噹共建區航站樓1層主體結構滿堂架支撐繫統,又為下部城際鐵路施工創造封閉、安全的蓋挖環境,確保兩者能同步施工。該聯閤施工方案在確保施工安全、解決垂直運輸、縮短工期方麵進行瞭積極探索,為新鄭國際機場T2航站樓縮短總工期180d以上,創造瞭較大的經濟和社會效益。
정주신정국제궤장T2항참루건축면적48?45만m2,항참루?~?축하천유성제철로、지철통과,해구역간칭공건구。량자공기균교위긴장,수재비외계인소간우하시공,차성철상부위항참루행리계통공제중심점지구역,전통적선심후천시공안배무법만족총진도수요。경과다차설계우화화연토,학정료성제철로개알시공정체사로,즉공건구상부설계54m장전환대량,기만족하부통차공간수요,우가장과도범위내항참루하재통과전환량전지지하승태,량상부포설패뢰가조작평태,기충당공건구항참루1층주체결구만당가지탱계통,우위하부성제철로시공창조봉폐、안전적개알배경,학보량자능동보시공。해연합시공방안재학보시공안전、해결수직운수、축단공기방면진행료적겁탐색,위신정국제궤장T2항참루축단총공기180d이상,창조료교대적경제화사회효익。
The built?up area of Xinzheng International Airport terminal T2 is 484?5 thousand square meters, and there crosses an intercity railway and a subway engineering below the terminal from axis 12 to 15, whose area is short for jointly constructed zone. Time limit for the both projects is tight, the construction needs a condition without external factors, in addition traditional construction method of first deep?then shallow can’ t satisfy the total progress due to the control center of baggage system area above the intercity railway. After many times of design optimization and research, integrated thinking of intercity railway covered?excavation construction is defined. This paper designed transfer beams with a length of 54 meters above the jointly constructed zone, which not only meets the lower traffic space and will deliver the terminal load in span range to the underground caps through transfer beams. There lays a bailey frame platform on the transfer beams to act as full scaffold support system for the main structure of terminal within the jointly constructed zone, and on the other hand it creates a closed and safe qualification for covered?excavation construction of lower intercity railway, ensures that both can be constructed synchronously. The joint construction scheme actively explored the aspects of ensuring the construction safety, resolved the vertical transportation and shortening the time limit for the construction, saved the time limit of Xinzheng International Airport terminal T2 over 180 days and created great economic and social benefits.