Industrial Engineering Journal
2015年
2期
127~132
,共null页
关键链项目管理 独立时差 非关键链 接驳缓冲
關鍵鏈項目管理 獨立時差 非關鍵鏈 接駁緩遲
관건련항목관리 독립시차 비관건련 접박완충
critical chain project management;independent float;non-critical chain;feeding buffer
加入接驳缓冲后可能导致关键链与非关键链产生资源冲突,非关键链溢出等问题,使得关键链调度计划的制定再次复杂化。为优化接驳缓冲的计算,在根方差法的基础上,运用独立时差这一项目网络提供的隐性安全时间,区分非关键链上的活动;并对非关键链上拥有独立时差的活动,改变Goldratt提出的所有非关键活动最晚执行策略,构建考虑独立时差的接驳缓冲设置方法。通过仿真实验,对采用不同接驳缓冲设置法得到的关键链调度计划进行比较;结果表明,新方法能减少接驳缓冲设置引发的问题,并较好地改善了项目工期,项目执行绩效。
加入接駁緩遲後可能導緻關鍵鏈與非關鍵鏈產生資源遲突,非關鍵鏈溢齣等問題,使得關鍵鏈調度計劃的製定再次複雜化。為優化接駁緩遲的計算,在根方差法的基礎上,運用獨立時差這一項目網絡提供的隱性安全時間,區分非關鍵鏈上的活動;併對非關鍵鏈上擁有獨立時差的活動,改變Goldratt提齣的所有非關鍵活動最晚執行策略,構建攷慮獨立時差的接駁緩遲設置方法。通過倣真實驗,對採用不同接駁緩遲設置法得到的關鍵鏈調度計劃進行比較;結果錶明,新方法能減少接駁緩遲設置引髮的問題,併較好地改善瞭項目工期,項目執行績效。
가입접박완충후가능도치관건련여비관건련산생자원충돌,비관건련일출등문제,사득관건련조도계화적제정재차복잡화。위우화접박완충적계산,재근방차법적기출상,운용독립시차저일항목망락제공적은성안전시간,구분비관건련상적활동;병대비관건련상옹유독립시차적활동,개변Goldratt제출적소유비관건활동최만집행책략,구건고필독립시차적접박완충설치방법。통과방진실험,대채용불동접박완충설치법득도적관건련조도계화진행비교;결과표명,신방법능감소접박완충설치인발적문제,병교호지개선료항목공기,항목집행적효。
Inserting feeding buffer in non-critical chain may lead to new problems, such as new resource conflict, non-critical chain overflow, etc. These problems further complicate the resource constrained pro- ject scheduling. In order to optimize the sizing of feeding buffer, based on root square error method (RSEM) , independent float is applied to solve the feeding buffer setting in critical chain project manage- ment theory. Using independent float wish is the hidden safety time in project network, the activities on non-critical chain are differentiated. Aiming at the non-critical activities which have independent float, and changing the latest time execution strategy proposed by Goldratt, the new feeding buffer sizing ap- proach is built. At the end, experimentation of different plans using various feeding buffer sizing methods has been done by means of simulation for contrastive analysis. Results show that the new approach reduces the problems caused by the feeding buffer inserting and improves the due date and execution performance of project.