通过对空分装置增压机设备、配管进行分析,认为增压机三回一配管连接设计不当是造成空分装置增压机振动异常的根本原因。为此,采用了合理的减振措施,有效降低了空分装置增压机的异常振动幅度,使机组振动值维持在37.0μm 左右。
通過對空分裝置增壓機設備、配管進行分析,認為增壓機三迴一配管連接設計不噹是造成空分裝置增壓機振動異常的根本原因。為此,採用瞭閤理的減振措施,有效降低瞭空分裝置增壓機的異常振動幅度,使機組振動值維持在37.0μm 左右。
통과대공분장치증압궤설비、배관진행분석,인위증압궤삼회일배관련접설계불당시조성공분장치증압궤진동이상적근본원인。위차,채용료합리적감진조시,유효강저료공분장치증압궤적이상진동폭도,사궤조진동치유지재37.0μm 좌우。
By analysis of equipment and piping of the booster of air separation unit,it is considered that the improper design of 3 back to 1 piping connection of the booster is the root cause for abnormal vibration of the booster of the air separation unit.Therefore reasonable vibration reduction measures are adopted,the abnormal vibration amplitude is reduced effectively,the vibration value of the unit is kept at about 37.0μm.