杨尚欢%王瑞星%王平%于常先%马云庆
楊尚歡%王瑞星%王平%于常先%馬雲慶
양상환%왕서성%왕평%우상선%마운경
盘区式采场%脉内联络巷%采矿成本
盤區式採場%脈內聯絡巷%採礦成本
반구식채장%맥내련락항%채광성본
Panel type stope%Connection roadway within mineral vein%Mining cost
三山岛金矿较大矿体主要用房柱交替式盘区上向分层充填采矿法回采,每个采场布置一条采场联络道,增加了采矿成本。为减少采场联络道的掘进和压顶工程量,采用在采场下盘布置一条沿矿体走向的脉内联络巷的方式回采,可以减少采场联络道数量,缩短采准工程的施工时间。通过对同一矿块应用2种采准方式对比,优化后的采场联络道的掘进量和压顶量分别减少15509.52 m3和16682.42 m3,分段巷、分段联络巷和泄水井的工程量共减少2966.82 m3,由于矿体分布不规则,下盘脉内巷道增加废石掘进量8925.72 m3。整个采场的采准工程量可节约26233.04 m3,节省了大量掘进成本,经济效益和社会效益显著。
三山島金礦較大礦體主要用房柱交替式盤區上嚮分層充填採礦法迴採,每箇採場佈置一條採場聯絡道,增加瞭採礦成本。為減少採場聯絡道的掘進和壓頂工程量,採用在採場下盤佈置一條沿礦體走嚮的脈內聯絡巷的方式迴採,可以減少採場聯絡道數量,縮短採準工程的施工時間。通過對同一礦塊應用2種採準方式對比,優化後的採場聯絡道的掘進量和壓頂量分彆減少15509.52 m3和16682.42 m3,分段巷、分段聯絡巷和洩水井的工程量共減少2966.82 m3,由于礦體分佈不規則,下盤脈內巷道增加廢石掘進量8925.72 m3。整箇採場的採準工程量可節約26233.04 m3,節省瞭大量掘進成本,經濟效益和社會效益顯著。
삼산도금광교대광체주요용방주교체식반구상향분층충전채광법회채,매개채장포치일조채장련락도,증가료채광성본。위감소채장련락도적굴진화압정공정량,채용재채장하반포치일조연광체주향적맥내련락항적방식회채,가이감소채장련락도수량,축단채준공정적시공시간。통과대동일광괴응용2충채준방식대비,우화후적채장련락도적굴진량화압정량분별감소15509.52 m3화16682.42 m3,분단항、분단련락항화설수정적공정량공감소2966.82 m3,유우광체분포불규칙,하반맥내항도증가폐석굴진량8925.72 m3。정개채장적채준공정량가절약26233.04 m3,절성료대량굴진성본,경제효익화사회효익현저。
The large orebodies in Sanshandao gold mine are mined mainly by the method of room and pillar alternating upper layer filling on the panel,each stope is arranged a connection roadway,so, the mining cost is increased.In order to reduce the tunneling and coping quantities of stope connection roadway,arrange a connection roadway within mineral vein along with the direction of orebody tend so as to reduce the amount of stope connection roadways and shorten the mining engineering construction time. The applications results of the two mining methods of the same ore block are analyzed,the analysis results show that the tunneling and coping quantities are reduced 15 509.52 m3 ,16 682.42 m3 respectively and the engineering quantities of the segmented lane,piecewise connection roadway and drainage well are re-duced 2 966.82 m3 by adopting the improved mining method.Due to the irregular distributed orebodies, the amount of waste rocks tunneling of the footwall roadway within mineral vein is increased 8 925.72 m3 .The whole stope mining quantities can be reduced 26 233.04 m3 ,therefore,the tunneling cost can be saved,the economic and social benefits are significant.