采矿与安全工程学报
採礦與安全工程學報
채광여안전공정학보
Journal of Mining and Safety Engineering
2015年
5期
771-777,785
,共8页
半煤岩巷道%数值模拟%截割顺序%灰色关联分析%方案优选
半煤巖巷道%數值模擬%截割順序%灰色關聯分析%方案優選
반매암항도%수치모의%절할순서%회색관련분석%방안우선
half-coal rock roadway%numerical simulation%cutting sequence%gray correlation analysis%scheme optimization
为了解决薄煤层条件下半煤岩巷道快速综掘的煤矿工程问题,针对半煤岩巷道快速综掘截割顺序设计与优化,采用三维快速拉格朗日法建立了数值计算模型,分析了不同截割顺序下分步开挖的围岩应力演化特征、剪切应变增量和剪切应变率的分布形态。基于灰色关联理论,建立了不同开挖方案的围岩位移与破裂范围分析模型,计算得到各参评方案的关联度分别为0.63,0.76,0.81和0.73,综合数值模拟与理论计算确定了最优综掘截割方案,最后结合具体工程对方案进行了验证。实践表明,先下后上、自右而左的倒“S”形综掘截割顺序可实现半煤岩巷道的最优化综掘,监测结果也表明了其合理性与可行性。
為瞭解決薄煤層條件下半煤巖巷道快速綜掘的煤礦工程問題,針對半煤巖巷道快速綜掘截割順序設計與優化,採用三維快速拉格朗日法建立瞭數值計算模型,分析瞭不同截割順序下分步開挖的圍巖應力縯化特徵、剪切應變增量和剪切應變率的分佈形態。基于灰色關聯理論,建立瞭不同開挖方案的圍巖位移與破裂範圍分析模型,計算得到各參評方案的關聯度分彆為0.63,0.76,0.81和0.73,綜閤數值模擬與理論計算確定瞭最優綜掘截割方案,最後結閤具體工程對方案進行瞭驗證。實踐錶明,先下後上、自右而左的倒“S”形綜掘截割順序可實現半煤巖巷道的最優化綜掘,鑑測結果也錶明瞭其閤理性與可行性。
위료해결박매층조건하반매암항도쾌속종굴적매광공정문제,침대반매암항도쾌속종굴절할순서설계여우화,채용삼유쾌속랍격랑일법건립료수치계산모형,분석료불동절할순서하분보개알적위암응력연화특정、전절응변증량화전절응변솔적분포형태。기우회색관련이론,건립료불동개알방안적위암위이여파렬범위분석모형,계산득도각삼평방안적관련도분별위0.63,0.76,0.81화0.73,종합수치모의여이론계산학정료최우종굴절할방안,최후결합구체공정대방안진행료험증。실천표명,선하후상、자우이좌적도“S”형종굴절할순서가실현반매암항도적최우화종굴,감측결과야표명료기합이성여가행성。
In order to solve the coal mine engineering problem of the rapid combined excavation in thin seam half-coal rock roadway, aiming at the design and optimization of combined excavation cutting sequence, the numerical model for analyzing the stress evolution of surrounding rock, the shape presentation of shear strain increment and shear strain rate under different excavation se-quence has been established by using three-dimensional fast Lagrangian method in this paper. The displacement and rupture range analysis model of different excavation scheme has also been estab-lished based on the grey relation theory, and the correlation degree of each scheme has been ob-tained with the result of 0.63, 0.76, 0.81 and 0.73. Finally an optimal combined excavation cutting scheme has been determined based on the numerical simulation and theoretical calculations, which has been verified by the concrete project. The engineering practices have indicated that the com-bined excavation cutting sequence of“down-up, right-left”can achieve the optimal combined ex-cavation in half-coal rock roadway. Meanwhile, the monitoring results have also proved its ration-ality and feasibility.