结合某高桩码头升级改造工程,阐述原码头拆除后,在原码头排架间的沉桩技术,以及在沉桩区域受周边构筑物影响大、地质条件复杂的环境下,采用振动锤与柴油锤联合沉桩的新技术,为类似工程的沉桩施工提供借鉴。
結閤某高樁碼頭升級改造工程,闡述原碼頭拆除後,在原碼頭排架間的沉樁技術,以及在沉樁區域受週邊構築物影響大、地質條件複雜的環境下,採用振動錘與柴油錘聯閤沉樁的新技術,為類似工程的沉樁施工提供藉鑒。
결합모고장마두승급개조공정,천술원마두탁제후,재원마두배가간적침장기술,이급재침장구역수주변구축물영향대、지질조건복잡적배경하,채용진동추여시유추연합침장적신기술,위유사공정적침장시공제공차감。
Based on a high-piled wharf upgrading project,we expound the piling technology,i.e.piling between bents of the original wharf after demolishing the original wharf,and the new piling technology which combines the vibration hammer with the diesel hammer in the area seriously influenced by the neighboring structures and with complicated geologic conditions,to serve as reference for the piling construction of similar projects.