软土深基坑%支护结构%m 值%弯矩%单纯形法%光顺样条法
軟土深基坑%支護結構%m 值%彎矩%單純形法%光順樣條法
연토심기갱%지호결구%m 치%만구%단순형법%광순양조법
soft soil deep foundation pit%supporting structure%m value%bending moment%simplex method%smoothing spline fitting method
基于实际软土深基坑工程,依据施工各工况实测位移,分别采用单纯形法位移反分析对基坑支护结构设计参数 m值和光顺样条法拟合对地下连续墙弯矩进行分析,并判定设计值和预测值之间的相互关系,为设计和施工提供一定的理论依据。根据单纯形法反演得到优化位移与实测位移基本接近,验证了反分析方法的可靠性,对设计参数 m 值可取其下限来控制基坑的最大变形。根据光顺样条法拟合求得曲率的基础上分别按弹性刚度和短期刚度进行弯矩估算,可得地下连续墙最大弯矩变化规律基本一致,且在基坑开挖初期,地下连续墙弯矩可以通过弹性刚度法估算墙体的弯矩承载力,随着基坑的开挖,地下连续墙弯矩实际更接近于规范短期刚度计算值。
基于實際軟土深基坑工程,依據施工各工況實測位移,分彆採用單純形法位移反分析對基坑支護結構設計參數 m值和光順樣條法擬閤對地下連續牆彎矩進行分析,併判定設計值和預測值之間的相互關繫,為設計和施工提供一定的理論依據。根據單純形法反縯得到優化位移與實測位移基本接近,驗證瞭反分析方法的可靠性,對設計參數 m 值可取其下限來控製基坑的最大變形。根據光順樣條法擬閤求得麯率的基礎上分彆按彈性剛度和短期剛度進行彎矩估算,可得地下連續牆最大彎矩變化規律基本一緻,且在基坑開挖初期,地下連續牆彎矩可以通過彈性剛度法估算牆體的彎矩承載力,隨著基坑的開挖,地下連續牆彎矩實際更接近于規範短期剛度計算值。
기우실제연토심기갱공정,의거시공각공황실측위이,분별채용단순형법위이반분석대기갱지호결구설계삼수 m치화광순양조법의합대지하련속장만구진행분석,병판정설계치화예측치지간적상호관계,위설계화시공제공일정적이론의거。근거단순형법반연득도우화위이여실측위이기본접근,험증료반분석방법적가고성,대설계삼수 m 치가취기하한래공제기갱적최대변형。근거광순양조법의합구득곡솔적기출상분별안탄성강도화단기강도진행만구고산,가득지하련속장최대만구변화규률기본일치,차재기갱개알초기,지하련속장만구가이통과탄성강도법고산장체적만구승재력,수착기갱적개알,지하련속장만구실제경접근우규범단기강도계산치。
Based on the practical deep foundation pit engineering of softsoil and the measured dispracement of construction condition,simplex method for displacement back analysis of foundation pit retaining structure disign paramener m (supporting structure design parameter)was analyzed.The smothing spline fifting method of under ground continuous wall bending moment were also studied.The design value and the mutual relation ship be-tween the predicted values were used to provide certain theoretical basis for the design and construction.Accord-ing to the simplex method,the optimal displacement and the measured displacement are obtained,and that veri-fies the reliability of the inverse analysis method.Besides,the m value of the design parameters can be used to control the maximum deformation of the foundation pit.According to the smoothing spline fitting method which was used to obtain the curvature based respectively according to the elastic stiffness and short -term stiffness of bending moment estimation,underground continuous wall maximum bending moment changes are basically the same.In the early foundation pit excavation,the underground continuous wall bending moment can be used through the elastic stiffness method to estimate wall bending moment capacity.With the excavation of foundation pit,underground continuous wall bending moments is closer to the regulate short -term stiffness calculation val-ue.