铁道建筑
鐵道建築
철도건축
Railway Engineering
2015年
10期
105-110
,共6页
王渭明%王冲%曹正龙%孙捷城
王渭明%王遲%曹正龍%孫捷城
왕위명%왕충%조정룡%손첩성
交叠隧道%二次衬砌%支护控制%二次变形
交疊隧道%二次襯砌%支護控製%二次變形
교첩수도%이차츤체%지호공제%이차변형
Overlapping tunnel%Secondary lining%Support control%Two-stage deformation
青岛地铁2 号线枣李区间隧道下穿3 号线泉李区间隧道,交叠段隧道围岩以强风化花岗岩为主,岩体破碎.为保证地铁正常铺轨及长期安全运营,开展了二衬支护控制研究.通过理论分析确定出二衬最佳支护时段,并提出三种二衬支护方案,利用数值模型分析各方案对交叠段围岩拱顶沉降、二衬结构变形及应力、塑性区形态特征的影响.最终提出交叠隧道二衬支护的最优方案为:在交叠区影响范围外,3 号线在隧道初支变形趋于稳定后施作二衬;在交叠区段,2 号线开挖完成且3 号线二次变形稳定后对其施作二衬.模拟结果验证了理论分析的正确性,为交叠隧道二衬支护控制提供了技术指导.
青島地鐵2 號線棘李區間隧道下穿3 號線泉李區間隧道,交疊段隧道圍巖以彊風化花崗巖為主,巖體破碎.為保證地鐵正常鋪軌及長期安全運營,開展瞭二襯支護控製研究.通過理論分析確定齣二襯最佳支護時段,併提齣三種二襯支護方案,利用數值模型分析各方案對交疊段圍巖拱頂沉降、二襯結構變形及應力、塑性區形態特徵的影響.最終提齣交疊隧道二襯支護的最優方案為:在交疊區影響範圍外,3 號線在隧道初支變形趨于穩定後施作二襯;在交疊區段,2 號線開挖完成且3 號線二次變形穩定後對其施作二襯.模擬結果驗證瞭理論分析的正確性,為交疊隧道二襯支護控製提供瞭技術指導.
청도지철2 호선조리구간수도하천3 호선천리구간수도,교첩단수도위암이강풍화화강암위주,암체파쇄.위보증지철정상포궤급장기안전운영,개전료이츤지호공제연구.통과이론분석학정출이츤최가지호시단,병제출삼충이츤지호방안,이용수치모형분석각방안대교첩단위암공정침강、이츤결구변형급응력、소성구형태특정적영향.최종제출교첩수도이츤지호적최우방안위:재교첩구영향범위외,3 호선재수도초지변형추우은정후시작이츤;재교첩구단,2 호선개알완성차3 호선이차변형은정후대기시작이츤.모의결과험증료이론분석적정학성,위교첩수도이츤지호공제제공료기술지도.
T he tunnel between Zaoshan station and Licun station of Qingdao metro line 2 under-crosses Quanli interval tunnel of line 3 and surrounding rock of overlapping tunnel is mainly composed of strongly weathered granite,rock mass of which are broken. In order to ensure the normal track layout and long-term safe operation of subway,secondary lining support control was studied. T he optimal supporting time of secondary lining was identified by theoretical analysis,three secondary lining support schemes were put forward,and the influence of each scheme on vault settlement of overlapping surrounding rock,structure deformation and stress of secondary lining and morphological characteristics of plastic zone was analyzed by numerical model. T he optimal scheme of overlapping tunnel secondary lining support is as follows: the secondary lining of line 3 should be constructed after primary support deformation tends to be stable outside the area of the overlapping,and the secondary lining of line 3 should be constructed after line 2 excavation finishes and two-stage deformation of line 3 is basically stable in overlapping area. Simulation results demonstrated the validity of the theoretical analysis,which would provide a technical guidance for secondary lining support control of overlapping tunnel.