惠州蓄能水电厂%黑启动%程序流程
惠州蓄能水電廠%黑啟動%程序流程
혜주축능수전엄%흑계동%정서류정
Huizhou Pumped Storage Hydropower Station%black start%procedure
蓄能电站是电网重要的调峰调频电站,也是黑启动电源之一。针对电网事故中,电站的黑启动能力对电网恢复输送电的重要性,介绍了惠州蓄能水电厂黑启动程序流程,分析了整个黑启动过程,可为类似项目的程序设计提供参考。
蓄能電站是電網重要的調峰調頻電站,也是黑啟動電源之一。針對電網事故中,電站的黑啟動能力對電網恢複輸送電的重要性,介紹瞭惠州蓄能水電廠黑啟動程序流程,分析瞭整箇黑啟動過程,可為類似項目的程序設計提供參攷。
축능전참시전망중요적조봉조빈전참,야시흑계동전원지일。침대전망사고중,전참적흑계동능력대전망회복수송전적중요성,개소료혜주축능수전엄흑계동정서류정,분석료정개흑계동과정,가위유사항목적정서설계제공삼고。
Pumped storage power stations are of great importance to electric power grid because they are usually acting as the load balancing and frequency regulation stations and also the power sources of black start .In case of a power grid ac-cident, the black start capability of power stations is crucial for the restoration of power grid .The black start procedure used in Huizhou Pumped Storage Hydropower Station is introduced and analyzed , which could be a useful reference for similar projects .