超大超深基坑%坑中坑%开门式出土%工期
超大超深基坑%坑中坑%開門式齣土%工期
초대초심기갱%갱중갱%개문식출토%공기
large ultra-deep pit%secondary excavation%open door type unearthed%duration
本文论述了超大超深基坑中,以坑中坑的方式在支护桩上开设洞口先行开挖土方再结构施工,坑中坑施工进度不受大基坑土方开挖及支护施工进度的影响。既节约了总体施工工期,又节约了施工成本,取得了较好的经济和社会效益。
本文論述瞭超大超深基坑中,以坑中坑的方式在支護樁上開設洞口先行開挖土方再結構施工,坑中坑施工進度不受大基坑土方開挖及支護施工進度的影響。既節約瞭總體施工工期,又節約瞭施工成本,取得瞭較好的經濟和社會效益。
본문논술료초대초심기갱중,이갱중갱적방식재지호장상개설동구선행개알토방재결구시공,갱중갱시공진도불수대기갱토방개알급지호시공진도적영향。기절약료총체시공공기,우절약료시공성본,취득료교호적경제화사회효익。
This article discusses the large ultra-deep pit, open the hole and excavate earth retaining pile first in the form of secondary excavation, and then carries out the structure constr-uction, the construction schedule of secondary excavation is not af ected by the big pit earth excavation and supporting con-struction. This method not only saves the overal construction duration, but also saves the construction costs, and achieves g-ood economic and social benefits.