水电站%围堰残梗%危害%处理措施
水電站%圍堰殘梗%危害%處理措施
수전참%위언잔경%위해%처리조시
hydropower station%cofferdam stubble%harm%tre-atment measures
本文针对沙湾水电站投入运行后泄洪冲沙闸坝下防冲槽内防冲砼块下沉、移位,周边河床淘刷形成冲坑问题,进行了探讨和原因分析。由于电站进入运行期,泄洪冲沙闸随时可能泄放水,相对施工期施工难度大,本文介绍了导流排水、临时围堰残梗拆除、冲坑回填实施方案。
本文針對沙灣水電站投入運行後洩洪遲沙閘壩下防遲槽內防遲砼塊下沉、移位,週邊河床淘刷形成遲坑問題,進行瞭探討和原因分析。由于電站進入運行期,洩洪遲沙閘隨時可能洩放水,相對施工期施工難度大,本文介紹瞭導流排水、臨時圍堰殘梗拆除、遲坑迴填實施方案。
본문침대사만수전참투입운행후설홍충사갑패하방충조내방충동괴하침、이위,주변하상도쇄형성충갱문제,진행료탐토화원인분석。유우전참진입운행기,설홍충사갑수시가능설방수,상대시공기시공난도대,본문개소료도류배수、림시위언잔경탁제、충갱회전실시방안。
This paper aiming at problems that scour prevent-ion concrete block is sinking, shift in anti-scour trench under water flushing sites after Shawan hydropower station put into operation, framing the scouring pit around the river by under-mining, makes the discussion and reason analysis. Because the power station into operation period, release flood waters sedi-ment flushing sluice may release at any time, it is relatively di-fficult than construction period, this paper introduces the diver-sion drainage, temporary cofferdam demolition, stubble scour pit backfil scheme.