隧道%进洞段%大管棚%施工方案
隧道%進洞段%大管棚%施工方案
수도%진동단%대관붕%시공방안
tunnel%holed section%pipe shed%construction sch-eme
文章首先介绍了超前大管棚的性能特点和适用条件,根据依托工程具体工程地质条件提出了适用大管棚进洞的施工方法,然后详细介绍了该隧道大管棚工法的施工过程和施工中需要注意的事项,为具体的洞口段进洞施工提供方案支持。
文章首先介紹瞭超前大管棚的性能特點和適用條件,根據依託工程具體工程地質條件提齣瞭適用大管棚進洞的施工方法,然後詳細介紹瞭該隧道大管棚工法的施工過程和施工中需要註意的事項,為具體的洞口段進洞施工提供方案支持。
문장수선개소료초전대관붕적성능특점화괄용조건,근거의탁공정구체공정지질조건제출료괄용대관붕진동적시공방법,연후상세개소료해수도대관붕공법적시공과정화시공중수요주의적사항,위구체적동구단진동시공제공방안지지。
This paper introduces the characteristics and appli-cation conditions of large advance pipe roof, according to the geological conditions proposes the specific engineering project construction method for large pipe shed into the hole, and then introduces the mat ers need to pay at ention to the construction process and construction of the tunnel pipe shed method, to pr-ovide support for the specific scheme of holed section const-ruction.