本文以深圳市某拟建大型地铁车站为例,利用有限元软件 Midas/Civil 模拟了叠合墙地铁车站盖挖逆作法的整个施工过程。旨在推动繁华市区叠合墙地铁车站盖挖逆作法的应用,并为国内外类似工程提供一定的参考。
本文以深圳市某擬建大型地鐵車站為例,利用有限元軟件 Midas/Civil 模擬瞭疊閤牆地鐵車站蓋挖逆作法的整箇施工過程。旨在推動繁華市區疊閤牆地鐵車站蓋挖逆作法的應用,併為國內外類似工程提供一定的參攷。
본문이심수시모의건대형지철차참위례,이용유한원연건 Midas/Civil 모의료첩합장지철차참개알역작법적정개시공과정。지재추동번화시구첩합장지철차참개알역작법적응용,병위국내외유사공정제공일정적삼고。
This article takes a planned large subway station in Shenzhen as an example and uses the finite element software Midas/Civil to simulate the whole construction process of co-ver and cutop down method in the composite walsubway st-ation. The author aims at promoting the application of cover and cutop down method in the composite wal subway station of prosperous downtown, and provides some reference for the similar projects at home and abroad.