系杆拱桥%钢管拱肋分段%排架布置
繫桿拱橋%鋼管拱肋分段%排架佈置
계간공교%강관공륵분단%배가포치
tied-arc bridge%steel tube arch rib section%bent arrangement
本文阐述了长兴岛新开港水闸外移改建工程,根据分段安装最不利荷载,验算排架安全稳定,设计排架支撑系统。逐段对称吊装形成整体后进行焊接,再向拱肋内对称顶升泵送砼形成整体拱梁,最后拆除排架支撑系统。
本文闡述瞭長興島新開港水閘外移改建工程,根據分段安裝最不利荷載,驗算排架安全穩定,設計排架支撐繫統。逐段對稱弔裝形成整體後進行銲接,再嚮拱肋內對稱頂升泵送砼形成整體拱樑,最後拆除排架支撐繫統。
본문천술료장흥도신개항수갑외이개건공정,근거분단안장최불리하재,험산배가안전은정,설계배가지탱계통。축단대칭조장형성정체후진행한접,재향공륵내대칭정승빙송동형성정체공량,최후탁제배가지탱계통。
This article expounds reconstruction project of sluice outward at Changxing Island Xinkai Port. According to the most unfavorable load, the article checks the security and stability of the bent, and then designs the support system of bent. In order to form ensemble, it can be hoist symmetrical y one by one, then welding. In order to form the whole arched girder, the pumping concrete can be fil ed to symmetrical jacking in the arch rib, and then the bent support system can be removed final y.