城市建筑
城市建築
성시건축
URBANISM AND ARCHITECTURE
2014年
26期
201-201,203
,共2页
一次施工%阶段加载%施工找平%施工补偿
一次施工%階段加載%施工找平%施工補償
일차시공%계단가재%시공조평%시공보상
a one-time construction%phase load%level equali- zation in construction%construction compensation
本文以广州超高层建筑混凝土结构施工过程中为研究对象,通过有限元Midas/gen进行了一次性施工加载和阶段加载分析。表明了竖向位移在一次性加载时为252 mm,阶段加载时为225 mm。并提出了严格控制施工找平和阶段施工补偿的方法。
本文以廣州超高層建築混凝土結構施工過程中為研究對象,通過有限元Midas/gen進行瞭一次性施工加載和階段加載分析。錶明瞭豎嚮位移在一次性加載時為252 mm,階段加載時為225 mm。併提齣瞭嚴格控製施工找平和階段施工補償的方法。
본문이엄주초고층건축혼응토결구시공과정중위연구대상,통과유한원Midas/gen진행료일차성시공가재화계단가재분석。표명료수향위이재일차성가재시위252 mm,계단가재시위225 mm。병제출료엄격공제시공조평화계단시공보상적방법。
This paper took the construction process of con- crete structure of the super high-rise building in Guangzhou as the research object, analyzing the one-time construction loa- ding and loading stages by the finite element method of Mi- das/gen. The research showed that the vertical displacement is of 252 mm in the disposable loading, and 225 mm when on the loading stages. And methods were put forward to strictly co- ntrol the level equalization in construction and to be applied in the construction compensation phase.